Timeline of our build

May 2013 - We chose this floorplan on a whim! We were set on a Barrington Floorplan. Like this:
http://www.vibeliving.com.au/images/grand_cayman_brochure.pdf
We love this floor plan - it really suits our family needs but ultimately, for the same money we get more with this original:
http://static.beechwoodhomes.com.au/images/designs/fp_327.pdf, we only made slight modifications and will still make a few minor changes once we are in!

We drove up to Oran Park town to check out the Barrington display again and chat with the salesperson who could not give us the answers we wanted on the day. On the way back I suggested to John that we stop and look at Beechwood as we never had. I instantly fell in love with the Bedarra. It is too wide for our block! We got chatting to a couple in the Verdehlo Four and they told us what changes they were making and how reasonable Beechwood were. I grabbed a copy of the floorplan and we havent looked at any other floorplans!

It was almost perfect for us. We wanted single storey, five bedrooms, master at the front, kids at the back and open kitchen/living/dining!
We requested a tender.

July

We paid our initial deposit as acceptance of tender.

September

We were told everything was ready to go to council. Yay. It's getting close, or so we thought.....













October








We were in and out of council within eight days. Five days later we signed contracts and chose all the important colours and accessories.

December



The all important commencement letter from our lender took six weeks! And we already had
preapproval! It was the longest six weeks of my life......




Christmas and new year was a long break of four weeks in the industry!

January onwards

Benching 17/01/14
Piers 28/01/14
Slab 5/02/14
Water and electricity connected
Frames arrive 24/2/2014
Frames up 25/2/2014
Trusses arrive 26/2/2014
Trusses up 27/2/2014
Fascia and gutter onsite 28/2/2014
Fascia and gutter installed 6/03/14
Roof delivery 3/03/14
Roof and anticon installation 10/03/14
Window installation 10/03/14
Plumbing rough in 12 and 13/03 14
Bricks delivery 13/03/14
Bricks started 18/03/14
Bricks complete 26/03/14
Electrical rough in 25/03/14
Plumbing rough in 25/03/14
Cavity door framework delivered 28/03/14
Eaves ready to go 28/03/14
Support beam across garage in place 31/3/14
Bricks across support beam 2/4/14
Insulation in walls 2/4/14
Eaves put in 2/4/14
Water proofing first stage 4/4/14
Gyprock onsite 8/4/14
Gyprock started 14/4/14
Gyprock complete 17/4/14
Kitchen installed 17/4/14
Front door and internal doors installed 28/4/14
Pantry and Robes 28/4/14
Lock up 29/4/14
Bricks cleaned 6/5/14
Second coat water proofing 6/5/14
Bathroom tiles onsite 8/5/14
Skirtings done 8/5/14
Cornices started 8/5/14